CBAM currently covers steel, aluminium, cement, fertilisers, electricity and hydrogen. On 17 December 2025, however, the European Commission published a legislative proposal to widen the scope. It would bring around 180 downstream steel and aluminium products into the system and points to 1 January 2028 as the start date. The Council and the Parliament have each adopted a position, and the three institutions are now negotiating a common text.
If you process steel wire, fasteners, pipe fittings or aluminium profiles and sell into the EU, you may not be on the CBAM list today. In two years you might be. This article covers who wants what, what is still undecided, and what you can prepare while you wait.
What changes compared with today’s CBAM
At present CBAM lists raw materials and semi-finished goods by customs tariff code (CN code in the EU, GTİP in Türkiye). If a product is not listed, no CBAM declaration is required at import. That leaves a gap. A steel plate carries a carbon cost, while a part made from the same steel can fall outside it.
The Commission drafted the proposal to close that gap. According to the Commission, the products in scope contain on average 79 percent steel or aluminium. Examples it has given publicly include base metal mountings, cylinders, industrial radiators and casting machines. Most are industrial intermediate goods, and the share of household items is small.
The calculation logic matters too. Under the Commission text, the certificate obligation for a downstream product is tied to the embedded emissions of its steel and aluminium inputs, not to the whole product. So before CBAM reaches you, you will need to know how much metal sits in each part and where that metal came from.
Three positions
The rules are not law yet. Each institution is negotiating from a different text.
| Commission proposal | Council (general approach) | Parliament | |
|---|---|---|---|
| Date | 17 December 2025 | 12 June 2026 | Committee 9 July, plenary 15 September 2026 |
| Number of products | About 180 | About 200 | Above 450 |
| Further expansion | Fixed list | Annual Commission review from 2028 | Wider list |
The figures appear in the European Parliamentary Research Service (EPRS) briefing from September 2026 and in law firm comparison notes. For the Parliament list, sources give numbers between 453 and 457, so we say “above 450”.
One point deserves attention. The Council text adds a mechanism under which the Commission reviews every year whether to propose further downstream products. The list may not be drawn once and closed. A product outside it today could be added within a few years.
Anti-circumvention and resource shuffling
The proposal does more than add products. The same package contains measures against CBAM avoidance, and the three texts differ here as well.
- The Commission treats artificially adjusting a supply chain to benefit from lower default values as circumvention.
- The Council limits the scope to operators, importers and authorised CBAM declarants, and targets changing the country of the last substantial production step solely to obtain lower default values.
- The Parliament writes it more broadly. It treats practices as circumvention when their only purpose is to avoid CBAM and they have no economic, commercial or operational justification. Slightly modified goods and “resource shuffling” fall within that frame.
Resource shuffling means steering low-emission production to goods bound for the EU and high-emission production to other markets. We do not know which text will prevail. Still, if you are restructuring shipment flows for EU compliance, it is wise to document the commercial rationale now.
Scrap and input counting
Because the downstream calculation runs on the emissions of the metal inside the product, scrap rules become important. The three texts propose three different rules.
- The Commission counts pre-consumer steel scrap as a precursor and leaves post-consumer aluminium scrap out.
- The Council counts pre-consumer steel and aluminium scrap as precursors and keeps post-consumer scrap out.
- The Parliament counts aluminium scrap, including post-consumer, as a precursor. For steel, it reports pre-consumer scrap but does not count it.
For an aluminium processor this difference can be decisive. If your share of recycled aluminium is high, your emission value could change noticeably depending on which rule is adopted. Recording the scrap share of your inputs today will help whichever rule wins.
Timeline
Trilogue negotiations began at the end of September. According to a Mayer Brown note from October 2026, technical meetings started on 28 September and the first political trilogue took place on 20 October. A second and final political trilogue is provisionally set for 30 November 2026. The institutions aim to reach a political agreement before the end of 2026.
If that holds, the final product list and rules will be clear by early winter. If it slips, the uncertainty carries into 2027. Either way, 1 January 2028 is the application date cited for the proposal. That is roughly two years to prepare, but building a data infrastructure, collecting emission data from suppliers and bringing it into the ERP takes most companies about that long.
Check the product list first, then your inputs
Once the final list is published, the first job will be checking your tariff codes. The part you can prepare without waiting is the input side. For a processor, the CBAM burden comes from the steel and aluminium you buy. When your customer asks for the embedded emissions of your product, most of that value will be the emissions of the metal you purchased.
Steps you can take today:
- Map your bill of materials. How much steel or aluminium goes into each product? If your ERP material list does not show it, better to see the gap now.
- List your metal suppliers. Which mill, which country, which period?
- Ask suppliers for emission data. Do they have a verified per-tonne value, or are default values used? More in our article on supplier emission data.
- Record the scrap share. Split input lines into scrap-based and primary.
- Build batch traceability. Which metal batch went into which finished good must be on record. That is hard in an ERP without batch links.
- Talk to your buyers. Does your EU customer know about this extension, and which data will they ask for, by when?
We covered the gap between default values and actual data in a separate article. In short, without actual, verifiable data your buyer falls back on default values, which usually means a higher cost.
Where İkiz Eksen fits
The difficulty with downstream products is getting emission data to meet the bill of materials and purchase records. Running that on scattered spreadsheets creates a workload you cannot keep up with once buyers start asking. We build the chain of measurement, software and compliance on a turnkey basis. We collect meter and machine data at the plant, combine it with ERP and purchasing records on a Microsoft Azure data platform, and produce a report a verifier can read. With the experience from Qera, more than 550 customers, more than 15 sectors and more than 100 ERP projects, we work across Türkiye.
Related pages: green transition, twin transition and solutions. If you want a first assessment based on your bill of materials and metal purchases, get in touch.
Frequently Asked Questions
I export steel or aluminium downstream goods. Does CBAM already cover me?
No. Today only products on the current list are in scope. The extension has not been enacted. You will need to check your tariff code once the final list is published.
When does the extension start?
The Commission proposal points to 1 January 2028. Final negotiations between the Council and the Parliament are planned for the end of 2026. The exact date and list depend on the agreement the three institutions reach.
How many products will be covered?
Not known yet. The Commission proposes about 180, the Council about 200 and the Parliament above 450. The final number will be set by the trilogue outcome.
Will the CBAM cost for a downstream product be calculated on the whole product?
According to the Commission proposal, no. The obligation is tied to the embedded emissions of the steel and aluminium inputs. Confirm the detailed method against the implementing text when it appears.
Does using scrap help me?
Which scrap counts differs across the three texts. There is a shared direction on pre-consumer scrap and a split on post-consumer aluminium. Recording the scrap share of your inputs now will help whichever rule is adopted.
Sources: European Commission CBAM page and press release of 17 December 2025; European Parliamentary Research Service (EPRS), “Extension of CBAM scope to downstream goods and anti-circumvention measures” briefing (September 2026); Mayer Brown, “EU’s CBAM downstream extension and anti-circumvention amendments: the road to trilogue” (October 2026). Figures and dates are as of publication. The process is ongoing, so confirm the final text with the Official Journal of the EU and your adviser.